| TIME | EVENT | ORE | FUEL | AIR | |||||
| ABSOLUTE | RELATIVE | ELAPSED | LB | TOTAL | BUCKET | TOTAL | PRESSURE | SETTING | |
| 13:30 | start wood splint pre heat | ||||||||
| Long break for supplies delays start | |||||||||
| 15:00 | set charcoal fines base, start wood splints | ||||||||
| apply gentle air - adjustments to air system | |||||||||
| 15:41 | 0:00 | start main smelt sequence - fill with charcoal | 5 | #REF! | 5 | 1 | |||
| 15:48 | 0:07 | 1 | 6 | ||||||
| 15:49 | 0:08 | adjust air | 2 | 2 | |||||
| 15:51 | 0:10 | 1 | 1 | ||||||
| 15:52 | 0:11 | adjust air | 4 | 1.5 | |||||
| 15:54 | 0:13 | 0:06 | 1 | 7 | |||||
| 16:04 | 0:23 | 0:10 | 2 | 3 | 1 | 8 | |||
| 16:14 | 0:33 | 0:10 | 3 | 6 | 1 | 9 | |||
| 16:23 | 0:42 | 0:09 | 3 | 9 | 1 | 10 | |||
| 16:34 | 0:53 | 0:11 | 4 | 13 | 1 | 11 | |||
| 16:45 | 1:04 | 0:11 | 4 | 17 | 1 | 12 | |||
| 16:58 | 1:17 | 0:13 | 4 | 21 | 1 | 13 | |||
| 17:10 | 1:29 | 0:12 | 4 | 25 | 1 | 14 | |||
| 17:22 | 1:41 | 0:12 | 4 | 29 | 1 | 15 | |||
| 17:34 | 1:53 | 0:12 | 4 | 33 | 1 | 16 | |||
| 17:45 | 2:04 | 0:11 | 4 | 37 | 1 | 17 | |||
| 17:55 | 2:14 | 0:10 | 5 | 42 | 1 | 18 | |||
| 18:09 | 2:28 | 0:14 | 5 | 47 | 1 | 19 | |||
| 18:22 | 2:41 | 0:13 | 5 | 52 | 1 | 20 | |||
| 18:32 | 2:51 | 0:10 | slag fobs removed from blow hole | 6 | 58 | 1 | 21 | ||
| 18:43 | 3:02 | 0:11 | 6 | 64 | 1 | 22 | |||
| 18:55 | 3:14 | 0:12 | air adjustment / poke through bowl from top | 6 | 70 | 1 | 23 | ||
| 19:07 | 3:26 | 0:12 | 6 | 76 | 1 | 24 | |||
| 19:23 | 3:42 | 0:16 | adjust air | 7 | 83 | 1 | 25 | 4 | 1.5 |
| 19:37 | 3:56 | 0:14 | 8 | 91 | 1 | 26 | |||
| 19:49 | 4:08 | 0:12 | 4 | 95 | 1 | 27 | |||
| 19:57 | 4:16 | moved blow hole upwards | |||||||
| 19:59 | 4:18 | 0:10 | 6 | 101 | 1 | 28 | |||
| 20:10 | 4:29 | 0:11 | 4 | 105 | 1 | 29 | |||
| 20:16 | 4:35 | moved blow hole upwards | |||||||
| 20:26 | 4:45 | 0:16 | 4 | 109 | 1 | 30 | |||
| 20:34 | 4:53 | 0:08 | 4 | 113 | 1 | 31 | |||
| 20:44 | 5:03 | 0:10 | 6 | 119 | 1 | 32 | |||
| 20:52 | 5:11 | 0:08 | 6 | 125 | 1 | 33 | |||
| 21:10 | 5:29 | 0:18 | 6 | 131 | 1 | 34 | |||
| 21:15 | 5:34 | moved blow hole upwards | |||||||
| 21:19 | 5:38 | 0:09 | 1 | 35 | |||||
| 21:27 | 5:46 | 0:08 | Burn down phase begins | 1 | 36 | ||||
| 21:48 | 6:07 | start extraction | |||||||
| TOTAL | SMELT TIME | 6 | hrs | ||||||
| CHARCOAL | 150 | lbs | |||||||
| ORE | 131 | lbs | |||||||
| BLOOM (main mass only) | 17 | lbs | |||||||
| YIELD | n/a |