| CLOCK | ELAPSED | EVENT | AIR | CHARCOAL | ORE | ||||
| Icelandic Sod Build June 2015 | UNIT | COUNT | TOTAL | ADD | TOTAL | ||||
| gate | LpM | bucket | kg | scoop | kg | ||||
| 12:00 | Start Preheat | x 1.82 | |||||||
| Inner surface crumbles | |||||||||
| 12:30 | 30 | Start Charcoal - 5 Maple, 5 Oak | 9 | 10 | 10 | ||||
| 12:41 | 11 | All Rough to fill | Max | ||||||
| 12:50 | 9 | Touch off volitiles | |||||||
| 12:59 | 9 | First graded charcoal | 1 | 11 | |||||
| 1:04 | 5 | 1 | 12 | ||||||
| 1:10 | 6 | 1 | 13 | ||||||
| 1:18 | 8 | 1 | 14 | ||||||
| 1:24 | 6 | 1 | 15 | ||||||
| 1:29 | 5 | 1 | 16 | ||||||
| 1:44 | 15* | Too much heat loss out of front. Packed it with dirt and sod. Possibly missed a charcoal bucket | 1 | 17 | |||||
| 1:49 | 5 | Tried packing the front with mud, fire coming out between cinder blocks | 1 | 18 | |||||
| 1:59 | 10 | 1 | 19 | ||||||
| 2:06 | 7 | First Ore | |||||||
| 2:13 | 7 | 1 | 20 | 1 | 1 | ||||
| 2:22 | 9 | How do we know when the Sod is burning? How do we keep the heat? | 1 | 21 | 1 | 2 | |||
| 2:32 | 10 | 1 | 22 | 1 | 3 | ||||
| 2:43 | 11 | 1 | 23 | 1 | 4 | ||||
| 2:57 | 14 | Turere 17 deg. How do we keep the walls from moving? | 1 | 24 | 1 | 5 | |||
| 3:05 | 8 | 1 | 25 | 1 | 6 | ||||
| 3:13 | 8 | Rocks are shifting. Front of dirt pile has lots of give. Front is still burning faster than back. Placing ore in the middle third will ensure better drop | 1 | 26 | 1 | 7 | |||
| 3:29 | 16 | 1 | 27 | 1 | 8 | ||||
| 3:37 | 8 | 1 | 28 | 1 | 9 | ||||
| 3:48 | 11 | 1 | 29 | 1 | 10 | ||||
| 3:59 | 9 | 1 | 30 | 1.5 | 11.5 | ||||
| 4:09 | 10 | 1 | 31 | 1.5 | 13 | ||||
| 4:18 | 9 | 1 | 32 | 1.5 | 14.5 | ||||
| 4:32 | 14 | 1 | 33 | 2 | 16.5 | ||||
| 4:42 | 10 | Starting to pile the charcoal up into more of a mound | 1 | 34 | |||||
| 4:44 | 2 | filled more to make the mound | 1 | 35 | 2 | 18.5 | |||
| 4:55 | 11 | Why slow times? Perhaps not enough air for the volume | 1 | 36 | 2 | 20.5 | |||
| 5:08 | 12 | 1 | 37 | 2 | 22.5 | ||||
| 5:17 | 9 | 1 | 38 | 2.5 | 25 | ||||
| 5:30 | 13 | 1 | 39 | 2.5 | 27.5 | ||||
| 5:39 | 9 | Last charge of ore | 1 | 40 | 3.33 | 30.83 | |||
| 5:46 | 7 | Start of burn down | 1 | ||||||
| 5:58 | 12 | 1 | |||||||
| Unable to extract - left bloom & slag in place | |||||||||
| TOTAL | Charcoal | 83 kg | |||||||
| Ore | 31 kg | ||||||||
| Bloom | 7.7 kg | ||||||||
| Yield | 25% | ||||||||