Absolute Time |
Elapsed Time |
Notes |
1506h |
|
A hole 55cm across and 25 to 37 cm deep (depending on
which part of the not-even-remotely-level ground we measured
against). A base of dried clay was laid approximately 4 cm
thick (when compacted). |
1532h |
T+0:26 |
On this base we built a circle of 9 firebricks standing on
end (this produced a rough circle 22.5 cm deep and 27cm
across). The hole was then backfilled with soil and tamped
into place. |
1540h |
T+0:34 |
The airpipe was rested on this brick and ground outside
producing the 20 degree down angle we were looking for. A
second circle on fire bricks went on. |
1650h |
T+1:44 |
At this point is was necessary to mix up some clay to use
to caulk the seams between the bricks. During this time we
also measured the ore charges from some extra roasted ore we
had lying around. 8 chares each of 1 Kg were prepared. The
caulking was applied and the outside of the bricks was also
given a band of clay. |
1751h |
T+2:45 |
A third layer of bricks went up and was also caulked with
clay. This gave us a total stack height of 67.5 cm, a
diameter of 27cm, and a bowl of 22.5 cm depth below the
tuyure to hold the slag. |
1811h |
T+3:05 |
We then raised some large stone slabs into a box around
the smelter and backfilled with sand. Then it was time to
start a warming fire that would also dry the clay. |
1823h |
T+3:17 |
To stabilize the airflow, and help with our low numbers of
people, this year we were using an old vacuum cleaner with a
rheostat to control the power and hence the airflow. The air
was turned on to level "A" (just enough to start an air
flow). |
1910h |
T+4:04 |
Airflow was increased to "B". |
1945h |
T+4:39 |
Airflow was shut off for a moment while the smelter was
filled with charcoal. Airflow was then restored. This is a
good point to mention a minor change in our handling of the
charcoal. This year with our "fast" concept (and rapidly
approaching night) we did not screen the charcoal but did a
visual inspection to keep the chunk size down. Larger pieces
were broken up with an axe. |
1957h |
T+4:51 |
the charcoal level had dropped by 15 cm (more on the
tuyure side, less on the back). The smelter was re-filled
with charcoal. |
2001h |
T+ 4:55 |
The airflow was increased half way up to "C". This
produced a nice loud "jet-like roar" from the smelter. |
2008h |
T+5:02 |
Temperature check with the optical pyrometer. 2950 deg. F.
Too hot. So we reset the air to "B". More charcoal was added
as the level had dropped 10 cm. |
2020h |
T+5:14 |
It just wouldn't be us if SOMETHING didn't go wrong. This
time the power cut out and we lost airflow. For the next 19
minutes we had intermittent airflow. The good news is that
at this point we were only warming the smelter so it didn't
really impact us. Also during this time the lovely blue
flames of a reducing fire appeared above the charcoal. |
2033h |
T+5:27 |
10 cm of charcoal added (power still intermittent) |
2044h |
T+5:38 |
10 cm of charcoal added. |
2059h |
T+5:53 |
Temperature now 2580 (F) and the first charge or ore was
added. 7.5 cm of charcoal was also added. |
2114h |
T+6:08 |
Ore charge #2 was added along with 10cm of charcoal. |
2125h |
T+6:19 |
Ore charge #3 was added to the back half of the smelter
and 7.5 cm of charcoal. |
2134h |
T+6:28 |
Ore charge #4 was added to the back half of the smelter
along with 12 cm of charcoal. |
2144h |
T+6:38 |
Ore charge #5 added to the back half with 10cm of
charcoal. At this point charge #1 should have worked its was
down to the "hot spot" in front of the tuyure. Another
temperature check was made showing 2520 (F). |
2151h |
T+6:45 |
The burn seemed a little high to us so the air was reduced
to A+ 3/4. The "jet roar" had been getting louder for the
past little while. Reducing the airflow left the roar going
but without as much volume. |
2152h |
T+6:46 |
Ore charge #6 was added to the back half with 10 cm of
charcoal. By now the first two charges should have been in
the hot spot. |
2207h |
T+7:01 |
Ore charge #7 added to the back half with 10 cm of
charcoal. At this point the first 3 charges should be in
front of the hot pot. |
2222h |
T+7:16 |
10 cm of charcoal added. The first four charges should now
be in the hot spot. |
2237h |
T+7:31 |
10 cm of charcoal added. By now five charges should be in
the hot spot. |
2250h |
T+7:44 |
10 cm of charcoal added. At this point 6 charges should be
in the hot spot with the final charge only 5 cm higher.
Around this point we observed that additional yellow
(oxidizing) flame was appearing across the surface of the
charcoal. Lots of blue flame still. |
2303h |
T+7:57 |
The reduction charge was added across the clear burn line
(about 1/3 of the way back from the tuyure) along with 7.5
cm of charcoal. |
2319h |
T+8:13 |
10 cm of charcoal added. Yellow flames had mostly vanished
by this point. |
2331h |
T+8:25 |
7.5 cm of charcoal added. |
2343h |
T+8:37 |
10 cm of charcoal added. Some yellow flames are beginning
to reappear. The reducing charge should be about 10cm above
the hot spot. |
0002h |
T+8:56 |
The charcoal level had dropped 15 cm so we decided it was
time to empty the smelter. Note that it was now 2 minutes
after midnight -- a true DARK event! Airflow was reduced to
"A" |
0004h |
T+8:58 |
The first charcoal was scooped out the smelter. |
0015h |
T+9:09 |
|
0021h |
T+9:15 |
First two bricks are now visible and the bloom was very
apparent. |
0023h |
T+9:17 |
We used a large (wet) log to pound on the bloom while it
was still hot to consolidate it as much as possible before
removing it. |
0035h |
T+9:29 |
Two lumps of slag came out on the scoop. |
0036h |
T+9:30 |
The bloom was pulled out, set on a rock and pounded on by
Darrell. This was interesting to watch as you could see the
lump jump from the force involved but very little
compression was achieved. |
0039h |
T+9:33 |
Final photos of the bloom and head inside to celebrate! |