LAM 1 Smelt - May 30, 2009

CLOCK ELAPSED EVENT AIR     CHARCOAL     ORE  
            UNIT COUNT TOTAL UNIT TOTAL
      gage LpM P bucket   kg kg kg
                     
12:00   start wood splints pre-heat                
12:50   very gentle air (maintain burning)                
14:10   gentle air 26              
14:40   adjust air 70   2.5          
    ash level about 5cm below tuyere                
14:52 2:52 start main sequence                
                     
12:00   fill with graded charcoal       2 2      
12:13 :13 charcoal       1 3      
12:30 :17 charcoal       1 4      
12:35   air increase (by sound) 80 650 3          
12:46 :16 charcoal       1 5      
12:48   temperatures:                
    1= 1170 2 = 1375                
13:04 :18 charcoal       1 6      
13:11   first ore - as slug             1 1
13:21 :17 charcoal       1 7      
13:35 0:14 ore added as 1/2 kg       1 8   1 2
13:47 0:12 ore added as 1/3 kg       1 9   1 3
13:53   temperatures:                
    1 = 620 2 = 985 4 = 1245                
    5 = 1250 6 = 1140 7 = 1105                
    8 = 1040 top = 625                
14:05 :18 high slag level / ore as 1/2 kg       1 10   1.5 4.5
14:18 :13         1 11   1.5 6
14:35 :17         1 12   2 8
14:51 0:16         1 13   2 10
15:07 0:16         1 14   2 12
15:31   temperatures:       1 15   3 15
    1 = 720 2 = 960 4 = 1100                
    5 = 1100 6 = 1115 7 = 1000                
    8 = 870 top = 800                
15:42 :18         1 16   3 18
15:54 0:12 start burn down       1 17      
16:30 0:36 extraction (approximate)                
                     
  TOTAL charcoal                
    ore 18 kg              
    time (main) 4:30              
    bloom 4.9 kg              
    yield (corrected for water) 33%              

Last Updated on 12/6/09
By Darrell Markewitz